This chart represents a summary of projects currently being undertaken or planned from 2007 to 2011

Project Description Date Commenced Projected Finish Approximate Cost Fund Source Completion
Upgrade toilets in Room 15 2006 2006 $7,000.00 School 5YA 2006
Front of school planting 2006 2007 $8,000.00 School 5YA 2007
Basketball hoops 2007 2007 $800.00 Maintenance 2007
Upgrade School server/web/connections 2007 2007 $10,000.00 Castle Trust 2007
Cabling the school/ Installation 2007 2007 $60,000.00 School 5YA 2007
Fence rear boundary of school 2007 2007 $7,000.00 School BOT 2007
Upgrade/Install heat pumps- ICT/R5/Staff 2007 2007 $12,500.00 School 5YA 2007
Cabling the school/ Installation 2007 2007 $12,000.00 School 5YA 2007
Fence the school front & side  boundary 2007 2007/8 $56,000.00 MOE 2007
Library Upgrade 2007/8 2008/9 $300,000.00 School 5YA 2009
Purchase of computer hardware for classes 2008 2008 $30,000.00 School BOT 2008
Food Technology room 2008 2008/9 $30,000.00 School BOT and WDHB 2009
Installation of new systems website upgrade 2008 2008 $12,000.00 School BOT 2010
Shade cover in front of student commonroom 2008 2008 $65,000.00 Trusts/5YA 2010
Upgrade Room 15 2008 2008 $16,000.00 School 5YA 2010
Astroturf/paving 2010 2011 $53,500.00 School 5YA 2011
Extend fence 2010 2011 $ 3,739.00 MOE 2011
Leak Rectification 2011 2011 $21,000.00 School 5YA Current
Electrical Up-grade 2011 2011 $51,000.00 School 5YA Current
Breakout spaces 2011 Unknown To be tendered School 5YA Current